dates and information provided
are
tentative and subject to change and that will be
updating them whenever we receive more current information.
This information was
collected on: March 11th, so date ranges are based from that
date.
The new
Founder's Square park - The site plan has been approved by the
county and is ready to submit for building permits. Construction
should begin in 60 to 90 days and should take about four months to
complete. The goal is to have it completed prior to the fall event
schedule which begins in October '07.
The CVS -
CVS has full approvals and we are awaiting their current schedule.
The Tech
School/TCHS Relief Center - The Tech School is scheduled to be
completed for the Fall '07 school year.
The Live/Work
units & tenants - The Live Work units recently received
preliminary subdivision plan approval and can now be submitted to
the building department for permits. The units should go to
contract with individual businesses in mid April. At that time
there will be a clearer idea of the tenants. Construction will not
begin until 10 of the 11 units are under contract although currently
all 11 are reserved. If contracts are acquired in April,
construction should start in June with a completion schedule of
February '08.
The unopened or
unoccupied spaces in Town Center 2 - Unoccupied spaces are still
available for lease. Briantos recently received permits and could
possibly be ready and 90-120 days. The YMCA general opening is on
April 1st, founder opening was Thursday, March 29th.
The
status/timeline for Town Center 3 - Town Center 3 has no
timeline but is rather a five to seven year plan to build out of the
remainder of Town Center based on market demands. Town Center 3 is
a long-term project.
The Alafaya
Extension & Widening - No new information on the extension or
widening at this time.
Avalon Church
- Avalon Church is waiting to get data plat recorded, at which time
they will be able to pull building permits. The best guess for
completion is January '08 although the church may have a more
accurate schedule.
The Florida
Hospital Medical Rehabilitation Facilities - The rehab facility
has approval from DRC per a re-submittal to address comments. It is
approximately 30 days from getting full site plan approval plus 90
days for building permits. Construction should start August 1,
2007, with a 10 month construction schedule.
The Fairwinds
Bank, Ace Hardware & other businesses in the works - Fairwinds
is attempting to get building permits but require a plat first which
is about 30 days out. The construction should take about 120 days.
The best guess for completion is Fall '07. Negotiations are still
ongoing with Ace Hardware but there is no agreement at this time.
Avalon Shoppes and Offices should start construction in the next
120-180 days.
Avalon Traffic Concerns (Discussions in
Q&A Postings)
- Traffic speed and volume in alleys
- Traffic around Avalon Elementary
- Need for more traffic control signs and speed signs throughout the
villages
- Use of off the road vehicles and powered scooters on both our
walkways and roads, especially by young and unlicensed drivers.
|